Successful Transportation of Equipment for the Hoa Binh Hydropower Plant Expansion Project
Project Information:
- Project name: Hoa Binh Hydropower Plant Expansion Project
- Commodity: Stator and spare part
- Volume: 14 PKGS / 363.012 TONS/ 727.81 CBM
- Port of Discharge (POD): Hai Phong Port, Viet Nam
Vantage Logistics Scope of Work: Transportation from the port to Hoa Binh construction site
Time of shipment (TOS): 08/2024
Combined River and Road Transport: To ensure safety and efficiency, Vantage Logistics implemented a transportation plan combining river and road transport, optimizing costs and delivery time.
Handling of Oversized and Overweight Cargo: The equipment included packages with dimensions and weight exceeding standard limits. This required the technical team to develop a detailed plan and execute it with precision.
Port and road reinforcement: To guarantee the safe movement of the cargo, Vantage Logistics reinforced the port at Hai Phong and the roadways leading to the Hoa Binh hydropower site.
Safe and On-time Delivery: Despite challenging weather conditions during transportation, with careful preparation and extensive experience, Vantage Logistics successfully completed the delivery safely, and on schedule, and ensured the project’s quality.